2008-April_21th
Cascina - Apr. 21th - 24th
Monday (Apr. 21st):
14:00 - 19:00 R&D Review (G. Losurdo) Auditorium
G. Losurdo click here for programme.Tuesday (Apr. 22th):
8:30 - 13:00 R&D Review (G. Losurdo) Auditorium
G. Losurdo click here for programme.13:00 - 14:00 lunch
14:00 - 15:30 Plenary (Th. S. Bauer) Auditorium
B. Mours Collaboration News 15'A. Vicere Analysis News 10'
E. Tournefier Commissioning News 10'
G. Losurdo AdV News 10
M. Punturo Detector News 10'
A. Krolak Presentation of a new Group 15'
M. Barsuglia Presentation of a new Group 15'
15:30 - 16:00 coffee
16:00 - 19:00 Commissioning (E. Tournefier) Auditorium
L. Rolland News from VSR1 calibration (15')
B. Swinkels Summary of magnetic noise studies (15')
J. Marque Brewster versus cryotrap (15')
I. Fiori Environmental noise studies at low frequency (15')
F. Bondu Estimation of the frequency noise in the dark fringe induced by shotnoise,(15')
E. Calloni Update on thermal effects and simulation (15')
G. Vajente Locking with TCS (15')
H. Heitmann Alignment status and plans (15')
F. Carbognani E&S status and plans (15')
parallel: 17:30 - 19:00 Data Transfer (A. Viceré) Council room
A. Vicere IntroductionWednesday (Apr. 23th):
9:00- 11:00 Data Analysis (A. Viceré) Auditorium
G. Vedovato Towards VSR1 analysis using cWB: status and plans (20')
L. Bosi Web tool and a library for veto and segment lists management (20')
C.Palomba On the possibility to target CW signals from the Vela pulsar (20')
T.Bulik IC10 X-1: the immediate progenitor of a double black hole binary (45')
A.Viceré Hot issues for Virgo data analysis: discussion (15')
11:00 - 13:00 Electronics + SW (F. Carbognani) Auditorium
S. Cortese, Online Servers Upgrade, (5' + 5')N. Letendre, Status on New Control and DAQ Electronics: Timing, TOLM
(15'+5')
D. Passuello, Status on New DSP and Carrier board (10'+5')
D. Passuello, New DSP Compiler (15'+5')
E. Pacaud, New Control and DAQ Electronics basic support software libraries (15'+5')
G. Ballardin, Status on "phase 1" SCS Software upgrades (EServerDSP porting to New DSP) (15'+5')
D. Sentenac, New Global Control (15'+5')
A. Masserot, Integration plans + Discussion (10' + 10')
13:00 - 14:00 lunch
14:00 - 18:00 Detector (M. Punturo) Auditorium
start duration end
14.00 30 14:30 Virgo+ laser amplifier and PMC status (F. Cleva)
14:30 10 14:40 Discussion
14:40 10 14:50 Laser amplifier integration planning (E. Genin)
14:50 5 14:55 Discussion
14:55 15 15:10 IMC end mirror payload status and installation program (TBD)
15:10 5 15:15 Discussion
15:15 15 15:30 Laser lab electronics displacement (F. Carbognani)
15:30 5 15:35 Discussion
15:35 20 15:55 TCS report and next activities (A. Rocchi)
15:55 5 16:00 Discussion
16:00 10 16:10 Coffee break
16:10 15 16:25 BRDF measurements in the optics lab (B. Canuel)
16:25 10 16:35 Discussion
16:35 15 16:50 PD under vacuum activity report (V. Granata)
16:50 5 16:55 Discussion
16:55 15 17:10 Power stabilization upgrade proposal (F. Cleva)
17:10 5 17:15 Discussion
17:15 15 17:30 Status and planning Monolithic suspensions (TBD)
17:30 10 17:40 Discussion
17:40 20 18:00 Measurement and suppression of thermal effects:
In situ monitoring of weak distortions and high power
Faraday Isolator (E. Khazanov)
18:00 - 19:00 Rehearsals (F. Ricci) Auditorium
Thursday (Apr. 24th):
9:00 - 13:00 VSC (B. Mours) Councilroom
1) News- EGO Council
2) MOU with GEO
3) AdVirgo system managers; Appointment
4) Detection committee; Discussion
5) Decisions to be made for:
- Commissioning, (Commissioning run of end of May)
- Detector,
- Data analysis,
- Advanced Virgo,
- Speakers bureau,
- Editorial board,
- Outreach.
Please bring only items that require decisions.
6) AOB.
Break
Group leaders only
1) Application of the POLGRAW group
2) Application of the APC group
3) AOB